UHN Chemistry Lab Automation Prince George, BC
Prince George, B.C.
Client
Northern Health Authority
Architect
DCYT Architecture Inc.
Engineer
NRS Engineering
General
Western Industrial Contractor
Project Type
Health Care
Location
Prince George, B.C.
Construction Sector
Institutional
Status
Completed Project - December 6, 2023
Scope included demolition and renovation of approx. 160 sq.m. of the existing Lab Chemistry, located on level 0, for the installation of the new automated Siemens Atellica. There was substantial HVAC and Electrical Distribution upgrades to accommodate this new lab automation system.