Barkman Concrete Plant Phase 1 MV SWG


Merritt, BC

 
03. Main.jpg

Client

6825347 Manitoba

Architect

Sharon Wang

Engineer

FALCON Engineering Ltd.

General

Acres Enterprises Ltd

Project Type

Utility

Location

Merritt, BC

Construction Sector

Industrial

Status

Completed Project - August 9, 2022

25KV Substation and Medium Voltage VFI Switch Gear for new Concrete Plant

Scope included 2 Way VFI, HV BCH Meter Cabinet, 3 Way VFI, and a 2.0MVA Oilfilled Xfmer.

Fun Fact:

This was the first S&C BC Hydro approved 3 Way VFI switch installed in the province. A culmination of 5 years of R&D for S&C and FPEI are proud to have installed there first one!

Derek,  

 You don't know me, I am the Barkman lead electrician at Merritt. I wanted to thank you for the excellent energization procedure and FLHA.   Well done.

Brent Norman

RSE, CET.